This past week (week commencing 24 May) has seen progression move more swiftly than predicted, which has resulted in groundwork starting on the left-hand side near the Wendleburie Garden:
1. Delivery of stone – Complete.
2. Setting out of stones – Complete.
3. Digging out of pathways opposite the top carpark – Complete.
4. Stoning up of pathways opposite the top carpark – Complete.
5. Digging out of pathways adjacent to the solar panels – Complete.
6. Digging out of pathways adjacent to the prison fencing – Complete.
7. Digging out of pathways in the meadow adjacent to the solar panels – work in progress.

Planned works for next week (week commencing 1 June) are:
1. Delivery of stone.
2. Setting out of stones.
3. Digging out of pathways on the left-hand side adjacent to the prison fencing.
4. Stoning up of pathways in the meadow adjacent to the solar panels.