This past week (week commencing 1 June) has seen progression on various preparation works for new pathways and memorial gardens.
Taken delivery of stone and setting out of stoning has been completed – digging out of pathways on the left side of the Garden of Remembrance adjacent to the new prison site has also been completed, with stoning up of pathways in the meadow on the opposite boundary continues to progress.

Planned works for next week (week commencing 7 June) are:
Delivery of additional stone for the continued stoning up of pathways on right side of the Garden of remembrance, with further stoning up of pathways in the meadow adjacent to the building. Further stoning up of pathways to the left side of the Garden of Remembrance.

Excavation works for installation of dropped curbs, to service access to the 3 new memorial gardens from existing relevant carpark areas.